Logistics

    • date: 06.11.2017
    • time: 10:00 - 15:00 CEST
    • venue: NORDUnet office Kastrup (tentative)
    • VC room for remote participation: 63246252

Agenda

  1. In-depth topics (2 hours)
    1. Nordic ideas and planning for GN4-3
    2. Next GÉANT network - roadmap, Nordic views, preparation
  2. Lunch (45 minutes)
  3. 2018 Meeting Calendar
    1. January meeting + topical workshop?
  4. Updates (45 minutes)
    1. GN4 update
      1. GN4-3 status
      2. geteduroam
      3. InAcademia operations
    2. GÉANT Update
    3. Big Users
      1. ESS
      2. EISCAT-3D
    4. Tenders
    5. NDN Next Gen process, meetings
    6. Shibboleth Consortium
    7. Pacific Research Platform & Data Transfer Nodes
  5. Country / NORDUnet updates (max. 15 minutes per NREN)
    • FUNET
    • SUNET 
    • UNINETT
    • DeIC 
    • RHnet 
    • NORDUnet 
  6. AOB

Participants

Notes

  • Country Updates
    • FUNET:
      • Fibre procurement done
      • Deadline for equipment offers 10.11,17
      • Deployment to start Q2/18
      • Piloting campus-network-a-a-Service.  Huge initial demand. Consider kicking off some sort of Nordic workshop or make it topic on CTO Forum meeting.  Also, is it topic for GN4-3.
      • Splitting into a FUNET network team, Data Centre team.  Recruiting.
      • Zoomi to be launched Q4/17
      • Backup as a service in pilot; to launch H2/18
      • FUNET CERT certified as Trusted Introducer
    • SUNET
      • Campus network support strategically important.  It really is a longterm project that need good analysis and design. I has to be standard and automated. SUNET is developing a reference design. SUNET is requesting budget to develop the service over the next three years.
      • Is this for GN4-3 or is it for a GÉANT TF?
    • UNINETT
      • Split into infrastructure company and services company.  34 out of 80+ moving into new entity - education (LMS, digital exams), Campus administration, cloud services and procurement. Also bringing on board two other education and research  entities.  New entity will in total be 200 people, of which 100 will be in Oslo. Network, middleware, FEIDE, network services to remain w UNINETT. 

Actions

  • No labels