  • 201404 - Public report
Skip to end of metadata
Go to start of metadata

You are viewing an old version of this page. View the current version.

Compare with Current View Page History

Version 1 Next »

Unscheduled:

  • April 28th: Work finished.
  • April 27th: Blown out rectifier on site caused total loss of power on 48V
  • April 21st: The red link to MAH did not restore after unannounced fiber maintenance. After reboot of transmission cards and rebuilt of cross-connects, the connectivity was restored.
  • April 14th: The north red network was down due to a fiber break outside Stockholm, this is now resolved.
  • April 4th: The transmission node was stuck in a reboot-loop after firmware upgrade. After replacement of both controller card and flash card, the node was back up.
  • April 2nd: The interface between LNU and Stockholm on the red network flapped. NO RFO was found.

Scheduled:

  • April 28th: Carrier performed a planned fiber maintenance outside Luleå.
  • April 9th: A broken transmission card in Luleå was replaced on the north red network.
  • April 8th: Supplier performed a planned maintenance

Scope

Unscheduled

Scheduled

Total

Hardware

1 pcs 02:15

1 pcs 01:35

2 pcs 03:50

Link

1 pcs 07:36

1 pcs 1d 13:53

2 pcs 1d 21:29

None

4 pcs 18:28

1 pcs 03:09

5 pcs 21:37

Routing

0 pcs

0 pcs

0 pcs

Software

0 pcs

0 pcs

0 pcs