Unscheduled:
- No issues
Scheduled:
- December 18th: Fiber provider performed maintenance in Abisko.
- December 4th: Supplier will perform a replacement of damaged fiber cable, Gällivare-Kiruna, took a lot longer than it should have.
- December 1 st: SUNET's supplier performed fiber maintenance in the North Blue network.
Scope | Unscheduled | Scheduled | Total |
---|---|---|---|
Hardware | 0 pcs | 0 pcs | 0 pcs |
Link | 0 pcs | 2 pcs 13:49 | 2 pcs 13:49 |
None | 0 pcs | 1 pcs 1:50 | 1 pcs 1:50 |
Routing | 0 pcs | 0 pcs | 0 pcs |
Software | 0 pcs | 0 pcs | 0 pcs |