- NORDUnet NGN update
- GÉANT Update
- Polar connect info
- Satellite project info
- Time & Frequency update
- Nordic Ansible workshop - dates and planning group
- EuroHPC Update
- NTW2019 Planning
- Round table updates - All
- AoB
Participants
- DeIC: Martin, Tangui
- SUNET: Valter, Pelle, Leif
- UNINETT: G´Vidar
- RHNET: Marius
- FUNET: Matti, Harri
- NORDUnet: Lars, Jørgen
Notes
- NDN NGN
- Two stretches migrated (OSL-STO, STO-CPH), one after holidays (OSL-CPH)
- fibre tender to go our in a couple of weeks
- Östersund-TRD link is on hand, fibre delivery soon
- FUNET to release procurement for HEL-STO fibre, offer is in place
- GÉANT update
- network:
- first NIAC meeting held to review RFI, so far looks good relative to budget. Baltic coordination meeting this afternoon
- NIAC has approved procurement
- Three items need further investigatopn: Ireland, Iberia, SEE
- Baltic ring on NREN fibre need more work
- SIG + Task Force preparation
- Valter to circulate report
- please all review groups and participations, we will discuss in a future meeting
- InfraEOSC-03
- GÉANT executive want to lead, BoD believe it's important and to investigate if it's possible to lead
- Costsharing
- Martin has joined the Cost sharing committee
- Adapting cost sharing to the future network is the main current task
- GÉANT BoD happy to have GÉANT participate in future ANA procurement
- network:
- Polar Connet
- Nordic Working group to be put together by NDN Board. All NRENs to nominate participant
- To explore options to Europe - Asia connectivity
- All work will be under NDA
- Ansible workshop
- week 14 october
- 2 days
- UNINETT has organiser
- we should organise brainstorming meeting for contents - early August
- SUNET is not doing Ansbile for network service automation - how to make it relevant for that? Or is that another workshop
- Is this Ansible only, or is it orchestration
- Leif: Can we really not do this during NTW? If so, are we using NTW in the best way?
- EuroHPC
- Northern Consortium pre-Exascale system was approved. Lots of things to be clarified during contract negotiation
- Congratulations to CSC on a job well done
- NTW19
- T&I hackathon on the Monday before
- Time and Frequency workshop on the Friday after
- It's really important to get the session descriptions up
- please get the information out
- Educational Services. Ulrika could not make it. Vegard Moen of UNIT has volunteered. He needs a person at each NREN to talk to.
- GÉANT would like to participate in the educational session
- Roundtable
- FUNET
- Panopto to be rolled out under European tender. FUNET collaborating with SURF
- Next step is LMS
- Very interesting outcome of OCRE. Very useful.
- FUNET 2020 now only 200 km from Kalix.
- Procurement of Stockholm and Umeå fibres to be procured this year
- DeIC
- Some confusion in Zoom pricing, MB + JQ to clarify
- Procurement for fibre for NDN NGN ongoing
- Has been awarded a EOSC project to develop sync-n-share services (with PSNC, CERN, SWITCH, SURFsara). 3 year project, infraEOSC-02, 6 M€
- DeiC now ISO 27001 certified. Doing so has been a major effort
- Iridium service initiative ongoing
- Faroe island project ongoing
- Greenland connectivity making less progress than hoped for
- UNINETT
- Launching Zoom. Focus on inter-operation with Canvas.
- Progress on geteduroam. Development pricing forthcoming. Should aim for a planning info package by 1 Sep, in order to make the September NDN BoD meeting
- planning to bundle eduVPN with CNaaS
- UNINETT has a new nationally funded, 4-year security services. First service is DNS Firewall
- SUNET
- e-compass study published (Valter to share). As a result, SUNET would like to do more visible coordination work
- RHnet
- Nothing to report at this time.
- NORDUnet
- Storage procurement has been concluded. Currently in standstill. JQ to circulate results and plans
- FUNET
- AOB
- EOSC-Nordic kick-off is in September (Espoo)
- EISCAT-3D network is delayed due to reindeer
...