Unscheduled:
* September 4th: The link towards HB and SP in the red network was down due to a broken transmission card. The card was replaced and traffic restored.
* August 30th: Link UMU-NDGF for LHCOPN project went down, was cause by a bad patch.

Scheduled:
* September 12th: Carrier performed a planned maintenance in Stackbo.
* September 23rd: Carrier performed a planned maintenance between Bålsta and Stockholm
* September 24th: Upgrade of SiteVision
{div}

Scope

Unscheduled

Scheduled

Total

Hardware

2 pcs 3d 00:09

0 pcs

2 pcs 3d 00:09

Link

0 pcs

2 pcs 6:37

2 pcs 6:37

None

0 pcs

0 pcs

0 pcs

Routing

0 pcs

0 pcs

0 pcs

Software

1 pcs 00:14

0 pcs